The Challenge
Aggressive project schedule
Coordination with a wide range of trades
The Solution
BIM collaboration with overhead trades allowed significant prefabrication
Precise coordination with other teams to prevent delays
Short interval planning
Compartmentalized work into six distinct projects
The Results
All construction milestones were met with no delays
Extremely high guest satisfaction at SunTrust Park
Specializations
Building Information Modeling (BIM)
Design/Assist
Pipe Shop Prefab
Sheet Metal Prefab

As part of a massive team, McKenney’s collaborated with a wide range of tradesmen, prefabricated much of the piping and sheet metal assemblies offsite—reducing installation time and allowing field supervisors to focus on short-interval planning and outfitting crews.
The work was compartmentalized into six distinct projects, each with its own supervisor, to accommodate short-term planning of the work and manpower. Thanks to combined efforts of all teams on the jobsite, design assist support and BIM expertise, the McKenney’s team met all the construction milestones without delays—contributing to the extremely high guest satisfaction rating for SunTrust Park and The Battery Atlanta.