Download PDF
Mastering a New System
PROJECT NAME
  • Indirect Evaporative Cooling (IEC) HVAC Installation
PROJECT LOCATION
  • North Carolina
PROJECT TEAM
  • General Contractor:
    Turner Construction
  • Contractor: McKenney’s, Inc.
SPECIALIZATIONS
  • Building Information Modeling
  • Design/Assist
MARKETS
  • Mission Critical
  • Science & Technology

cKenney’s installed an atypical HVAC system at the data center of a Fortune 100 company.

THE CHALLENGE

It was McKenney’s first time working for this customer, and although the teams are always mindful of the importance of safety, quality and productivity, on this project they were held to rigid quality requirements by the customer. The team installed and commissioned an

indirect evaporative cooling system—a cutting-edge energy efficient HVAC system—that required extensive planning to hit new installation milestones.

THE SOLUTION

The team devoted significant time to maintaining quality and productivity standards by pre-planning and coordinating with the owner, their subcontractors and the HVAC equipment manufacturer. The McKenney’s team

allocated resources using the strengths of employees that were more familiar with the new technology. Furthermore, additional project management leadership was dedicated to the site to ensure the project was properly managed and executed.

THE RESULTS

The team exceeded quality standards, project milestones and built a positive relationship with this new customer.

404-622-5000
info@mckenneys.com
1056 Moreland Industrial Boulevard
Atlanta, Georgia 30316
704-357-1200
info@mckenneys.com
3601 Performance Road
Charlotte, North Carolina 28214