Seamless Data Center Operations
PROJECT NAME
  • Large Data Center
PROJECT LOCATION
  • Norcross, Georgia
PROJECT TEAM
  • Owner: Communications
    Services Provider
  • General Contractor:
    Westin Construction
  • Engineer: Black & Veatch
SPECIALIZATIONS
  • Plumbing Shop Prefab
  • Energy Management
  • Pipe Shop Prefab
  • Sheet Metal Shop Prefab
MARKETS
  • Mission Critical
  • Central Plants

cKenney’s made significant upgrades to the mechanical systems infrastructure— including chillers, piping and pumps— without interrupting data center operations.

THE CHALLENGE

Critical equipment in the facility had to remain active, with optimal redundancy at all times.

The engineer and McKenney’s had to develop a detailed sequence of construction procedures.

THE SOLUTION

McKenney’s built a large steel platform in sections above the existing chillers. Each chiller was individually lifted to its section on the platform where it was reconnected quickly using prefabricated piping connections. Once startup and commissioning was completed

on the relocated chiller, the team began to work on the next chiller.

THE RESULTS

The complicated process was completed without any interruption to data center operations while adhering to facility security procedures. The customer expressed satisfaction with the quality and expediency of the work.